Posted on: September 17, 2020

[ARCHIVED] Downtown Paving Schedule

construction

Milling/Grinding will continue (Thursday) on Central ST from Pine ST to Maple. Once they complete Central, they will move to Vernon ST in afternoon.

All Milling should be completed by Friday Afternoon (pending no issues)


Paving: **All weather dependent**

Saturday Sept 19th

City Hall Ave, Nichols St, Pleasant St


Tuesday September 22nd

Main St


Wednesday September 23rd

Central St, Pine St (to West Lynde), and Vernon St


Once complete, a structure crew will come in and raise all structures to grade. This will take a few weeks.